Triangle Report
Semi Annual status update
District: Syangja
Period covered by this report: January to September 2014
Name of village |
Sanabhanjyang, NP-7 Named : Forest Village |
|||||||||||||||||||||||||||||||||||||||||||||
Was the Triangle procedure followed? Were there any deviations from the standard procedure? |
Yes, the villagers followed the triangle procedure and held settlement level planning in September. There were not any deviations. |
|||||||||||||||||||||||||||||||||||||||||||||
How many people were present at the village meeting? |
27 men/25 women, including 14 Dalits |
|||||||||||||||||||||||||||||||||||||||||||||
How many members are in the committee? |
5 men and 4 women, including2 Dalits
|
|||||||||||||||||||||||||||||||||||||||||||||
What were the issues raised at the village meeting? |
Water and sanitation, income generation activities, women empowerment, youth empowerment, school repairing, foot road, women Skill development, vegetables farming, road etc. |
|||||||||||||||||||||||||||||||||||||||||||||
What were the priorities presented by the committee? |
|
|||||||||||||||||||||||||||||||||||||||||||||
What did the villagers decide to spend the funds on? |
The villagers decide to spend Nrs 50,000.00 for foot trail construction, and Nrs 40,000.00 for goat raising from Triangle supported money. |
|||||||||||||||||||||||||||||||||||||||||||||
Has the committee received the funds yet? |
Funds are in transfer process, and will reach the village in October 2014, after completing the settlement planning and resource allocation plan in September. |
|||||||||||||||||||||||||||||||||||||||||||||
Activity plan: When are the activities going to be implemented? |
All planned activities will be started after Nepalese big festival Dashain and Tihar and finalized in December 2014 |
|||||||||||||||||||||||||||||||||||||||||||||
Who is responsible for the implementation? |
The village committee plays the vital role to implement all activities and after that VDC Secretary, VDC social Mobilizer and Triangle responsible person Hari also support to implement and monitor. |
|||||||||||||||||||||||||||||||||||||||||||||
How were the beneficiaries selected? |
After finishing the settlement level planning the village committees’ members again organized the meeting and make the criteria to distribution of money. Generally the villager followed some indicators for the distribution of money which is indicated by LGCDP(Local Government Community Development Programme):
|
|||||||||||||||||||||||||||||||||||||||||||||
Were there any disagreements – discussions about the priorities? What was the role of the Triangle facilitator? |
Before the training of settlement level planning, some of the villagers found that the Triangle donation could not fulfil all aspects of the wishes the villages had. However, the facilitator and Hari explained about the money and the supporting system from Triangle (getting to know how to influence VDC and DDC to get projects approved, and how to ask for better services). Specially ASK cooperate and fully focus on the settlement level planning process with the engagement of communities, give the information of the Triangle, and about the resources of the VDC block grant and the District Development Office possibilities of supporting the village. The villages have seen that the Triangle support to ASK and the villages, has given the villagers more tools for managing their own resources and influencing local bodies (VDC and DDC). |
|||||||||||||||||||||||||||||||||||||||||||||
Did the villagers have any comments/questions for the Triangle? |
With lack of awareness, it was difficult to manage the money the right way the previous year, but after villagers participated in settlement level planning, they realized and fully agreed to the method and found it was realistic and participatory. There was a request that ASK should provide more technical knowledge for the settlement level planning and development possibilities in the village. |
On-going activities – Status Update
Name of village/cluster |
Last visit: |
Progress in the reporting period |
Changes/delays/comments |
(Sanabhanjyang -NP 7) Named: Forest Village |
September 2014 |
1. Settlement level planning is completed. 2. All planned activities are under Implementation |
|
Reporting of Micro Loan
Use of Micro loan in 2014 |
|
Use of Micro loan until 2013 |
Micro loan total collected from pay back of loans: Nrs 150,000 (Nrs 1,00,000 from previous year + Nrs 50,000.00 from 2013)
|