Triangle Report
Semi Annual status update
District: Syangja
Period covered by this report: January to September 2014
Name of new village |
Dumsuwa Khola Orange Village- NP-13 |
|||||||||||||||||||||||||||||||||||
Was the Triangle procedure followed? Were there any deviations from the standard procedure? |
Yes, the villagers followed the triangle procedure and held settlement level planning in September. There were not any deviations. |
|||||||||||||||||||||||||||||||||||
How many people were present at the village meeting? |
30 men/28 women |
|||||||||||||||||||||||||||||||||||
How many members are in the committee? |
3 men and 4 women, including 1 Dalit
|
|||||||||||||||||||||||||||||||||||
What were the issues raised at the village meeting? |
Water and sanitation, Income generation activities, road, women empowerment, Vegetables farming etc. |
|||||||||||||||||||||||||||||||||||
What were the priorities presented by the committee? |
|
|||||||||||||||||||||||||||||||||||
What did the villagers decide to spend the funds on? |
The villagers decide to spend Nrs 35,000.00 for goat raising, Nrs 20,000.00 for Stool making training, Nrs 20,000.00 for vegetable farming in plastic house and Nrs 10,000.00 for bhattekhoriya spout conservation from Triangle supported money. |
|||||||||||||||||||||||||||||||||||
Has the committee received the funds yet? |
Funds are in transfer process, and will reach the village in October 2014, after completing the settlement planningand resource allocation plan in September. |
|||||||||||||||||||||||||||||||||||
Activity plan: When are the activities going to be implemented? |
All planned activities will be started after Nepalese big festival Dashain and Tihar and finalized in December 2014 |
|||||||||||||||||||||||||||||||||||
Who is responsible for the implementation? |
The village committee plays the vital role to implement all activities and after that VDC Secretary, VDC social Mobilizer and Triangle responsible person Hari also support to implement and monitor. |
|||||||||||||||||||||||||||||||||||
How were the beneficiaries selected? |
After finishing the settlement level planning the village committees’ members again organized the meeting and make the criteria to distribution of money. Generally the villager followed some indicators for the distribution of money which is indicated by LGCDP(Local Government Community Development Programme):
|
|||||||||||||||||||||||||||||||||||
Were there any disagreements – discussions about the priorities? What was the role of the Triangle facilitator? |
Before the training of settlement level planning, some of the villagers found that the Triangle donation could not fulfil all aspects of the wishes the villages had. However, the facilitator and Hari explained about the money and the supporting system from Triangle (getting to know how to influence VDC and DDC to get projects approved, and how to ask for better services). Specially ASK cooperate and fully focus on the settlement level planning process with the engagement of communities, give the information of the Triangle, and about the resources of the VDC block grant and the District Development Office possibilities of supporting the village. The villages have seen that the Triangle support to ASK and the villages, has given the villagers more tools for managing their own resources and influencing the those of the local bodies (VDC and DDC). |
|||||||||||||||||||||||||||||||||||
Did the villagers have any comments/questions for the Triangle? |
With lack of awareness, it was difficult to manage the money the right way the previous year, but after villagers participated in settlement level planning, they realized and fully agreed to the method and found it was realistic and participatory. There was a request that ASK should provide more technical knowledge for the settlement level planning and development possibilities in the village. |
On-going activities – Status Update
Name of village/cluster |
Last visit: |
Progress in the reporting period |
Changes/delays/comments |
Dumsuwa Khola -NP 13 |
September 2014 |
1. Settlement level planning is completed. 2. All planned activities are under Implementation |
|
Reporting of Micro Loan
Use of Micro loan in 2014 |
|