Reepa 2014 rapport (hele året, med kort status efter jordskælvene i april/maj 2015)

Home / Rapporter-Syangja / Reepa 2014 rapport (hele året, med kort status efter jordskælvene i april/maj 2015)
By saugat dhakal inRapporter-Syangja
ASKlogo Trianglenlogo lille

Triangle Annual Report from Village

Annual status update

District: Syangja
Period covered by this report: January to December 2014 with follow up after earthquake in May 2015

Name of village Reepa, NP-10
Was the Triangle procedure followed? Were there any deviations from the standard procedure? Yes, the villagers followed the triangle procedure and held settlement level planning in September. There were not any deviations.
How many people were present at the village meeting? 20 men/20 women in Settlement Level Planning- SLP
How many members are in the committee?

5 men, 4 women and   2 Dalits

Name of Committee Members Position
Krishna Thapa Chair-Person
Til Bahadur Gurung Secretary
Hum Bahadur Gurung Treasure
Anu Pangeni Member
Chandramaya Sharki Member
Lal sing Sarki Member
Prem Bahadur Gurung Member
What were the issues raised at the village meeting? Water and sanitation, repairing of school furniture, income generation activities, women empowerment, youth empowerment, irrigation, ponds conservation, school repairing, foot road, women Skill development, vegetables farming, road etc.
What were the priorities presented by the committee?
S.N. Name of Project Total Score of Project* Priority Potential Source of funding (Institution)
  Construction of community building 33 1 Triangle
  Repairing of school furniture 33 1 VDC
  Construction of road from VDC to Reepa 33 1 VDC
  Pucharghar drinking water supply 31 2 VDC
  Sumre drinking water conservation 31 2 Triangle
  Vegetables farming 30 3 Triangle
  Stool making training 26 4 Triangle
  Support to make the volleyball ground 25 5 Triangle
  Poultry business promotion 24 6 Triangle
  Goat raising 24 6 Triangle
  Fish keeping 23 7 Waiting
  Sewing and cutting training to women 23 7 waiting
  Pig raising 22 8 Waiting
What did the villagers decide to spend the funds on? The villagers decide to spend Nrs 20,000.00 for community building construction, Nrs 10,000.00 for Sumre drinking water stream conservation, Nrs 15,000.00 for vegetables farming, Nrs 10,000.00 for stools making from bamboo, Nrs 8,000.00 for youth club for repairing volleyball ground, Nrs 10,000 for poultry support and Nrs 15,000.00 for goat raising from Triangle supported Money.
Has the committee received the funds yet? Yes in October 2014, it was transferred.
Activity plan: When are the activities going to be implemented? All planned activities were completed, which are described below:

  • Nrs 20000 was spent to build the community house in the middle of the village.
  • Nrs 10000 was spent to repair the drinking water stream in the village.
  • Nrs 10000 was spent for the training of stool making from bamboo.
  • Nrs 8000 was spent for repairing of volleyball ground to youth club.
  • Nrs 38000 rupees invested for micro loan to women and poor’s income generation.
Who is responsible for the implementation? The village committee plays the vital role to implement all activities and after that VDC Secretary, VDC social Mobilizer and Triangle responsible person Hari also support to implement and monitor.

How were the beneficiaries selected?

After completed the settlement level planning the village committees’ members again organized the meeting and make the criteria to distribution of money. Generally the villager followed some indicators for the distribution of money which is indicated by LGCDP (Local Government Community Development Programme):

  • The family with no or very little land.
  • Poor house condition.
  • Lack of food for whole year.
  • Labours for others for livelihood.
  • Unemployed family.
  • No guarantee for settlement, etc.

Were there any disagreements – discussions about the priorities?

What was the role of the Triangle facilitator?

Some of the villagers found that the Triangle donation could not fulfil all aspects of the wishes the villages had. However, the facilitator and Hari explained about the money and the supporting system from Triangle (getting to know how to influence VDC and DDC to get projects approved, and how to ask for better services).

Specially ASK cooperate and fully focus on the settlement level planning process with the engagement of communities, give the information of the Triangle, and about the resources of the VDC block grant and the District Development Office possibilities of supporting the village. The villages have seen that the Triangle support to ASK and the villages, has given the villagers more tools for managing their own resources and influencing those of the local bodies (VDC and DDC).

Did the villagers have any comments/questions for the Triangle? With lack of awareness, it was difficult to manage the money the right way the previous year, but after villagers participated in settlement level planning, they realized and fully agreed to the method and found it was realistic and participatory. There was a request that ASK should provide more technical knowledge for the settlement level planning and development possibilities in the village. Now the money for micro-loan is increasing so it has to provide the account management knowledge also.

 On-going activities – Status Update

Name of village/cluster Last visit: Progress in the reporting period Changes/delays/comments
Reepa NP-10 Named: Orange Village

September

2014

1. Settlement level planning is completed.

2. All planned activities are under Implementation

  1. All the activities were delayed because of heavy and delayed rain, Local festival and giving approval from Ministry of Local Development for settlement level planning.   Implementation of all   activities is on-going. It is expected to be finalized in December.
  2. VDC is cooperating in the SLP process by assigning the social mobilize in training, workshop and planning exercise at village level.
Reepa NP-10 Named: Orange Village May 2015 All planned activities were completed There are no any comments and changes.

Reporting of Micro loan

Use of Microloan until end 2014 Micro loan total collected from pay back of loans: Nrs 226000 (188000 from previous year + Nrs 38,000 from 2014)

  • 26 families got the microloan Nrs 141000 (24 Persons*Nrs 5000, 1 person*Nrs 10000 and 1 person*11000) and started the goat raising.
  • 4 families got the microloan Nrs 45000 (2 Persons*Nrs 15000, 1 person*Nrs 10000 and 1 person*Nrs 5000) and started the small poultry business.
  • 3 families got the microloan Nrs 30000 (1 Person*Nrs 20,000 and 2 persons*Nrs 5000) and started the pig raising.
  • 2 families got the microloan Nrs 10000 (2 Persons*Nrs 5000) and started the vegetables farming.
Major Achievements from Previous Year
  • The 30 families who got loan for different kind of income generation activities (goat raising, pig raising, grocery shop, ginger farming and vegetables farming) in 2013, they got a lot of benefits and extra money ( Nrs 3000 to 30000) and spent it for the their children to better education, building houses, food and some clothes for the families and pay back loan to committee.
  • The women, children and the all villagers health situation improved because of improved smokeless stoves, the use of firewood is more economical and CO2 emission is less. Now they are happy and give many many thanks that support their village with new concept and now every Hhs have improved smokeless cook stove.
  • 2 Persons were also involved in proposal writing training organized by ASK and Triangle with the cooperation of VDC.
  • People from the village are continuing the regular saving, credit in sustainable way and almost all villagers are involved in one micro-credit group and the group is affiliated in VDC level multipurpose cooperative also.
Impact of Settlement level planning
  • Mrs Krishna Thapa (Chairperson of NP-10) has selected member for Integrated Planning Committee for the VDC level planning and the coordinator for ward citizen forum for her ward/village.

Some examples of activities supported by Trianglen

NP10 2014 2 1 NP10 2014 2 2
Community discussions Dhan Bahadur Gurung has started a poultry business
NP10 2014 2 3 NP10 2014 2 4
Indra Sunar has started raising pigs Bamboo stool made by people trained with the support of Trianglen
NP10 2014 2 5 Pig raising in the village has increased

Village situation after earthquake and aftershock

Six houses are totally collapsed and 25 houses are partially cracked. School building and the new community building also partially cracked. Many livestock sheds are cracked and damaged. People are requesting more shelter but the VDC distributed very few so the people are requesting us about the support.

NP10 2014 2 6 NP10 2014 2 7
Houses damaged by the earthquake

 

222 Posts
saugat dhakal
  • Previous PostReepa 2014 rapport (jan-sep)
  • Next PostReepa 2013 rapport (jan-okt)